Our Dismantling & Demolition Projects In Scunthorpe
Explore our dismantling and demolition projects from Scunthorpe and surrounding areas. PPS Demolition Ltd offers a transparent view of site clearance and recycling work to inspire your next undertaking.
​​
If you want to discuss your project, get in touch with us today.
FIRST-CLASS SERVICE
RELIABLE SERVICE
FULLY COMPLIANT
Eggborough Power Station – DSM Demolition Ltd
PPS Metal Recycling (PPS) was appointed by DSM Demolition Ltd (DSM) as a sub-contractor for associated works at the Eggborough Power Station site. The scope of work included:
-
Dismantling and processing of large and small transformers
-
Clearance of reusable pipework
-
Internal strip-out of stores
-
Dismantling and lifting operations for the alternator within the turbine hall
-
Dismantling and lifting operations for the pump house, including removal of an overhead gantry crane
-
Purchasing of ferrous and non-ferrous metals
All works were carried out in a phased sequence in line with the agreed programme timescales. Regular coordination was maintained between PPS and DSM to ensure smooth project delivery.
Project duration: August 2019 – February 2022 (Phased works)
Contract value: Between £2.5m – £3.0m
Key site constraints and challenges:
-
Coordination with ongoing site activities
-
Presence of residual COSHH substances within units
-
Fire risk and hot work operations
-
Working at height
-
Heavy industrial dismantling
-
Lifting operations
-
Heavy haulage logistics
Achievements:
-
Completion of works on time and within budget
-
Secured repeat contracts with DSM following the successful completion of each phase
Thornhill Power Station – White Tower Energy Ltd
PPS Metal Recycling (PPS) was appointed by White Tower Energy Ltd (WTE) as a subcontractor for works at Thornhill Power Station. The project involved:
​
-
Internal strip-out prior to mechanical demolition
-
Dismantling and lifting operations of the smoke flue
-
Purchasing of ferrous and non-ferrous metals
Works were conducted in a phased manner, adhering to programme timescales, with ongoing coordination between PPS and WTE throughout the project.
Project duration: March 2022 – July 2022
Contract value: Between £500,000 – £1m
Key site constraints and challenges:
-
Coordination with ongoing site activities
-
Fire risk and hot work operations
-
Working at height
-
Heavy industrial dismantling
-
Lifting operations
-
Heavy haulage logistics
Achievements:
-
Project delivered on time and within budget
-
Successful completion without any accidents or incidents